Installation of water borehole system for dairy farm at Tregony

Aqua source (SW) Ltd have successfully installed a water borehole system to work in conjunction with the farms existing Well, which has struggled to keep up with the farms demand as the dairy herd has increased. Aqua source carried out the complete system including bespoke design, drilling works , groundworks, and all necessary pump and filtration works.

Installation of water borehole system for dairy farm at Tregony Read More »

Installation of replacement private potable water main at Trewassick, Newquay

Aqua Source SW have used a chain trencher to lay 1200meters of 32mm MDPE pipe, bedded in sand with tracer marker tape. The replacement pipeline crossed a number of hedges which we used a mole to tunnel under and thus reduce hedge disturbance. Aqua Source SW replaced all meters and stop valves to the individual properties so as

Installation of replacement private potable water main at Trewassick, Newquay Read More »